Applies to: Agreement V3.0 · legacy V1.0/V2.0
Because the Agreement has been amended twice, and reliance arrangements documented under each version remain valid for the life of those studies.
- Version 1.0 (September 5, 2016 – September 30, 2020) was the original Agreement.
- Version 2.0 (October 1, 2020 – March 16, 2025) revised the insurance, conflict-of-interest, grant-congruence, and no-violation-of-law provisions so that the NIH Intramural Research Program and other federal agencies could participate. It was compatible with Version 1.0, so institutions did not need to re-sign unless they were entering a reliance arrangement with NIH.
- Version 3.0 (March 17, 2025 onward) is a significant amendment that reflects the 2018 Common Rule, opens the Agreement to more federal agencies, moves HIPAA responsibility to the Relying Institution, and adds an optional Indemnification Addendum. It is not compatible with earlier versions, so every institution signs a new Joinder Agreement. Since March 17, 2025 it is the only version that can be used for a new reliance arrangement, including adding a site to an existing study.
Arrangements made under Versions 1.0 or 2.0 before March 17, 2025 continue under those versions, and may be migrated to Version 3.0 if both institutions are V3.0 signatories and agree.